Agenda item

Minutes:

The Committee considered the undernoted report:

 

“1.0     Purpose of report

 

1.1       The Council’s Capital Programme is a rolling programme of investment which either improves existing Council facilities or provides new facilities. This report provides –

 

·        an update on the Capital Programme 13/14 which was presented to Committee on 24th March 2013

 

·        proposed recommendations for movement between the Capital Programme stages

 

·        specific project updates

 

·        an update on the capital financing for 2014/2015

 

2.0       Relevant Background Information

 

            Update on 2013/14 Capital Programme

 

2.1       Significant progress has been made in the delivery of the capital programme since it was agreed by SP&R Committee last March. Details of the current status and photographs of projects have been circulated. The Property & Projects department is happy to arrange site visits for Members/ Party Groups to Council funded capital project. 

 

2.2       Key highlights since the last quarterly report in November include -  

 

·        the successful relocation of the Belfast Welcome Centre to Donegal Square which opened in December 2013.  This £1.8million project was part funded by the ERDF

 

·        literally moving a river under Phase 1 of the £4m Connswater Community Greenway project with the realignment of Knock River in Orangefield Park at the end of January

 

·        the roll-out of Phase 3 of the Alleygating Programme with the majority of the gates to be installed across the city by the end of March

 

·        Super-Connected Belfast - the launch of the full voucher scheme on 14th Feb

 

·        MUGA programme - refurbishment work is well underway on a number of sites including Willowbank and New Lodge

 

      Capital Programme

 

2.3       Members have agreed that all capital projects must go through a three Stage process where decisions on which projects progress are taken by SP&R. This provides assurance as to the level of financial control and will allow Members to properly consider the opportunity costs of approving one capital project over another capital project. Importantly it will also enable Members to focus on delivering the projects which can have maximum benefits and investment return for the city and local areas.

 

      KEY ISSUES

 

      Capital Programme – Proposed movements - Projects recommended to move up a Stage

 

      Proposed movements from ‘Stage 1 – Emerging’ to ‘Stage 2 – Uncommitted’

 

2.4Members are asked to consider if they wish to progress the projects as outlined in Table 1 below from ‘Stage 1- Emerging project’ to ‘Stage 2- Uncommitted’ under the Capital Programme.  A Strategic Outline Case (SOC) has been completed for each of these which has examined (i) Background to the project; (2) Feasibility; (3) Affordability; (4) Deliverability and Sustainability.  Members are asked to note that at SOC level the affordability of a project is only examined at a high level and this is tested and challenged further during Stages 2 and 3.

 

Project

Project Review

Proposed Stage

 

City Hall

Works

Members will be aware an EQIA on Memorabilia

Was carried out last year and the outcomes reported to Committee in Nov 12. Following this an independent consultant was commissioned to undertake work in relation to the next steps for displays, the findings of which were presented to the Joint Diversity group in March.  Party Group briefings were subsequently held in April and May.  At this stage the Joint Diversity Group requested that the displays & memorabilia element be referred to the SP&R Committee as an Emerging Project as part of the City Hall project and that a composite SOC for all elements of the City Hall works be developed.  This was agreed by the SP&R Committee in September 2013.

 

As part of the development of the SOC, the Council commissioned independent consultants to a conduct a feasibility study into the creation of a memorabilia led visitor exhibition within the
East wing.  This study, which helped inform the SOC, has demonstrated that the project is feasible and has produced plans and designs to show how the project could work within the proposed space.

 

The SOC has also taken onto account at a very high level a number of other emerging issues including the Council’s corporate accommodation strategy, the impact of local government reform and transfer of functions.

 

The findings from the feasibility study and the SOC were presented to the Joint Diversity Group on 31st January and Party Group briefings on the City Hall works were subsequently held w/c 3rd February.

 

Members are asked to consider if they wish to advance this to Stage 2 – Uncommitted and the development of an outline business case.

 

 

 

Roselawn

Extensions

Members will be aware that the Council has a statutory duty to provide grave space.  Current provision has fallen below the minimum requirements of 4,500 new burial plots being available at all times.  The development of further grave space at Roselawn was therefore and Emerging Project on the Council’s Capital Programme.

 

The SOC proposes to create 7,300 new grave plots as well as the associated infrastructure.  Three phases are proposed – Phase 1 – 3500 new graves; Phase 2 – 2300 new graves, Phase 3 – 1330 new graves

 

Members are asked to note that this is a long term scheme and will provide provision up to 2025.  Members are asked to consider if they wish to advance this to Stage 2 – Uncommitted and the development of an outline business case.

Stage 2

Tamar Street

Members will be aware that the Council owns land in Tamar Street off the Newtownards Rd.  There is a modular building on part of the land which was previously leased by the Scout Association.  The East AWG had been approached by the Group who were interested in using the building and asked that this project be added to the Emerging Projects list in June.

 

Members are asked to note in relation to this project that the SOC has identified a number of emerging issues.

 

·        Goes against previous SP&R Committee decision to demolish building due to its bad state of repair (April 2012)

·        The group do not need to use the premises 24/7 and there are alternative facilities available in the neighbouring area – in addition to Connswater Community Centre there is also Walkway, Friendship Centre, Dee St Community Centre and Skainos

·        Any letting out of the building would have to go through and Expression of Interest process (it cannot just be given to one group)

·        The land is designated as ‘white-land’ and is therefore free from development constraints.  The Council also owns the adjoining land and this may facilitate the wider development of the site.

 

Members are therefore asked to consider if they wish to advance this to Stage 2 – Uncommitted and the development of an outline business case or if they wish to hold this and look at a wider masterplan for the site.

 

 

 

      Updates on capital projects

 

      Belfast Waterfront Exhibition and Conference Facility

 

2.6Members will be aware that one of the major projects under the Investment Programme is a proposed extension to the Waterfront to provide dedicated exhibition and conference facilities.  Funding for this project has now been secured with a letter of offer for £14.5million from ERDF and £4m from NITB together with the Council’s investment of £11m. This is a significant investment for the city and will significantly enhance the city’s economic infrastructure. Preparatory work is continuing with the enabling works due to go on ground at the end of March with main work commencing in the late summer.

 

      Tropical Ravine

 

2.7Members are asked to note that funding for refurbishment of the historic Tropical Ravine has now been secured with a letter of offer for £2.32million from the Heritage Lottery Fund. Preparatory work is continuing with the enabling works due to go on ground at the end of March with main work commencing in the autumn time.

 

2.8Members are asked to note that the Council’s Investment Programme set a target of levering in £50m over the course of the programme.  As highlighted in the Quarter 3 Finance report which is also on Committee for discussion today at the end of December nearly £30m of external funding had already been levered in.  With the addition of both the Waterfront and Tropical Ravine projects this brings the figure of levered in money to over £50million with additional monies still due to be levered in through a number of other projects including the Innovation Centre, the Creative Hub and the infrastructure at the North Foreshore. 

 

      Public Bike Share Scheme

 

2.9Members will recall that they agreed in June 2013 to move the Public Bike Share Scheme from a ‘Stage 2 – Uncommitted project’ to a ‘Stage 3 – Committed Project’.  At this stage this was moved to ‘Tier 0 – Schemes at risk’ as it was highlighted to Committee that the ongoing revenue implications for this scheme had not yet been agreed.  This meant that the scheme could be advanced to tender stage but that no construction contracts could be let until all outstanding issues were satisfactorily resolved.

 

2.10     The project aims to create a network of 30 docking stations supporting 300 bikes in the city centre. It is anticipated that it will facilitate cheap and accessible transport, as well as benefits such as increased tourism, improved health, and reduced congestion. Bike share schemes have proved very popular in cities across the world including London, Dublin and New York.

 

2.11     External funding of £698,700 was secured from DRD under the Active Travel Demonstration Projects for the project.  Members are asked to note that the Council’s bid for this figure was based on OBC for a Public Bike Hire Scheme which was commissioned by SIB.  At this time the OBC estimated that annual revenue costs for the operation/maintenance of such a scheme would be approx £370,000 per year. It should be noted that most public bike share systems do not meet their full operating cost through membership and user fees alone and, in addition to sponsorship/advertising revenue, some form of public sector subsidy is usually required.

 

2.12     Since June 2013 officers have worked hard on progressing this project.  An Invitation to Tender was advertised on the 4th November 2013 with the procurement was divided into two lots: Lot 1 – Design, supply, maintain and operate and Lot 2 –sponsorship.  Tenders are currently being evaluated and a detailed report will be brought back to Committee in March.

 

      Council Accommodation

 

2.13     Members will be aware that they agreed to move Council Accommodation from a ‘Stage 1 – Emerging project’ to ‘Stage 2- Uncommitted project’ on the capital programme in September last year.  An economic appraisal was commissioned on the back of this to help inform the development of a longer term strategy for the Council’s accommodation needs.  Members are asked to note that a separate report on Accommodation is on the agenda for discussion at today’s Committee.

 

      Innovation Centre and Creative Hub

 

2.14     Members will be aware that the Investment Programme included a range of projects designed to enhance the city’s economic infrastructure.  These included the development of a Creative Hub and an Innovation Centre.  These projects are both seeking funding under ERDF and it is anticipated that the outcome of these applications will be known shortly.  In the meantime given the tight timescales for the delivery of EU projects the Committee agreed that these projects could be worked at at risk. Separate reports in relation to acquisitions to facilitate these projects are on the agenda at today’s Committee

 

3.0       Capital Financing –Capital Programme 2014/15

 

3.1       The Council incurs capital expenditure and capital financing costs in the delivery of its capital programme.

 

·        Capital Expenditure is the expenditure incurred in the actual delivery of contracts e.g. the actual payments to the contractor for a construction contract. 

 

·        Capital Financing is the method the council uses to fund the capital expenditure. The capital financing costs include loan repayments (principle and interest) and revenue contributions (cash payments to repay or avoid taking out loans).

 

3.2       At its meeting on 21 June 2013 the SP&R Committee considered a report on the affordability of the leisure transformation programme and agreed an overall capital expenditure affordability limit of £105m for this. To support the capital financing of this capital investment the Committee agreed the following recommendations:-

 

·        To allocate, from the 1 April 2015, £3.23m of the £6m Belfast Investment Fund annual rates contribution to finance the £38m Olympia /Andersonstown schemes. (£2m: 14/15)

 

·        To set a target of £2m of additional rates income emanating from local government boundary changes being available to support the capital financing of the LTP. (£2m: 15/16)

 

·        To set a £2m efficiency savings target for leisure services as part of the LTP deliverable on the 1 April 2016 and that these savings are used for the purpose of leisure capital financing. (£2m: 16/17)

 

·        To include the £1.7m outstanding financing requirement in the Council’s Medium Term Financial Plan

 

      The incremental additional capital financing highlighted above has been included in the capital financing projections for 2014/15-2016/17 within this report.

 

3.3The delivery of the Capital Programme element of the Investment Programme will be matched by a phased increase in capital financing charges up to the capital financing limit over the life of the programme as all schemes within the programme are financed. The phased impact of the capital programme on the capital financing budget provides the opportunity for the council to allocate an element of the 2014/15 capital financing budget to finance feasibility works and non recurring schemes.

 

      Feasibility Fund 2014/2015

 

3.4The incremental nature of the Investment Programme means that there is the opportunity for the Council to ring fence part of the capital financing budget to provide a Feasibility Fund. The Feasibility Fund enables initial feasibility work to be undertaken on proposed projects to bring them to a point where Members can decide if they should be progressed as Capital Schemes, or Belfast Investment Fund (BIF) schemes. It is recommended that the contribution to the Feasibility Fund for 2014/15 be capped at £250k.

 

      Non-recurrent projects

 

3.5Members are asked to agree an allocation of £1million towards non recurring maintenance projects to be funded from the capital financing budget.

 

3.6Table 2 below summarises the outstanding loans and planned capital expenditure which will require financing up to 16/17. This covers all schemes detailed in Appendices B and C.

 

3.7 Table 2 - Capital Expenditure to 2016/17 – Current Programme

 

Outstanding Loans @ 31.03.13

£20,167,038

Capital Expenditure 2013/14

£8,444,905

Capital Expenditure 2014/15

£31,802,710

Capital Expenditure 2015/16

£52,839,139

Capital Expenditure 2016/17

£30,464,563

Total Capital Expenditure

£143,718,355

 

3.8Table 3 below provides a summary of the allocation of the capital financing budget for the above expenditure based on the capital financing proposals in Appendices E and F together with other non recurring schemes. 

 

3.9       Table 3 - Capital Financing to 2016/17 – Current Programme

 

 

2014/15

2015/16

2016/17

Loan Repayments

Existing Loan Repayments

£1,957,127

£4,503,049

£8,375,252

New Loans: Committed Schemes

£2,258,306

£3,009,101

£2,356,758

New Loans: Uncommitted Schemes

£287,616

£863,102

£1,044,947

Total Loan Repayments

£4,503,049

£8,375,252

£11,776,957

 

Revenue Funding

Committed Schemes

£4,731,925

£4,210,625

£2,511,300

Uncommitted Schemes

£0

£0

£0

Non Recurring Maintenance

£1,000,000

£0

£0

Feasibility

£250,000

£250,000

£250,000

Total Revenue Funding

£5,981,925

£4,460,625

£2,761,300

Less Capital Financing Budget

£13,370,000

£15,370,000

£17,370,000

Available Financing Budget

£2,885,026

£2,534,123

£2,831,743

 

 

3.10     As part of the proposed movements in the Capital Programme, the Committee is being asked to consider if they wish to move the three projects outlined below to Stage 2 – Uncommitted Projects. Table 4 below illustrates the impact of these movement with the following capital financing assumptions for the schemes:-

 

·        Tamar Street - £50k capital expenditure to be financed through a revenue contribution in 2014/15.

 

·        City Hall Works - £2m to be financed through loans over a four year repayment period.

 

·        Roselawn Extensions - £2.2m financed through loans of over a 25 year repayment period.

 

3.11     Table 4 – Capital Financing Impact to 2016/17 of Proposed Stage 1 Movements

 


 

 

 

2014/15

2015/16

2016/17

Available Financing Budget (From Table 2)

£2,885,026

£2,534,123

£2,831,743

Less Additional Financing Requirement

 

 

 

Tamar Street

£50,000

£0

£0

City Hall Works

£306,250

£578,750

£556,250

Roselawn Extensions

£0

£48,125

£84,000

Revised Available Financing Budget

£2,528,776

£1,907,248

£2,191,493

  

 

 

 

 

 

 

 

3.12     Table 4 above illustrates that the total of the capital financing budget available reduced to only £2.1m in 2016/17. This position is based on the financing of the committed and uncommitted projects included in Appendices B and C, together with the proposed Stage 1 movements referred to above. It should be noted that this does not include financing for the following potential future costs:-

 

·        The Emerging List projects included in Appendix D

 

·        The final phase of the LTP for which a financing source has to be identified

 

·        Any new capital schemes or non recurring maintenance or other re-instatement costs arising from the condition surveys on assets transferring from Lisburn/Castlereagh areas

 

·        The impact of the transfer of regeneration powers and its impact on capital expenditure by the Council

 

·        The Council’s Accommodation strategy

 

4.0Recommendations

 

4.1Members are asked to note the contents of this report and

           

      Movements

 

·        agree if the proposed  projects as outlined in Table 1 – City Hall Works, Roselawn Extensions and Tamar Street are progressed from ‘Stage 1 – Emerging’ to ‘Stage 2 – Uncommitted’ on the Capital Programme

 

      Project Updates

 

·        Belfast Waterfront Exhibition and Conference Facility – note that funding of £18.5m has been secured for this project (£14.5m from ERDF and £4m from NITB)

 

·        Tropical Ravine - note that funding of £2.32m has been secured for this project from the Heritage Lottery Fund (HLF)

 

·        Public Bike Share Scheme – agree to consider a detailed report on this at Committee next month

 

·        Council Accommodation – note that a separate report in relation to Council Accommodation is on the agenda for discussion at today’s Committee

 

·        Innovation Centre and Creative Hub – note that separate reports in relation to acquisitions to facilitate these projects are on the agenda at today’s Committee

 

      Levered in monies

 

·        note that with the external funding that has been secured for both the Waterfront and the Tropical Ravine that the Council has now levered in over £50million in external funding towards capital projects under its investment programme – this has exceeded the target outlined in the Programme with additional monies still due to be levered in through a number of other projects including the Innovation Centre and the Creative Hub. 

 

      Capital Financing

 

·        agree that £250,000 from the capital financing budget be ringfenced for Feasibility Fund

 

·        agree an allocation of £1million towards non recurring maintenance projects to be funded from the capital financing budget.”


 

 

            After discussion, it was

 

            Moved by Councillor Carson,

            Seconded by Councillor Hargey,

 

      That the City Hall Works – Memorabilia Project be advanced to Stage 2 of the Capital Programme and that a report providing a broad outline of the costs and the indicative budget for Stage 2 be submitted to the Committee for consideration at its meeting on 21st March.

 

            On a vote by show of hands ten Members voted for the proposal and seven against and it was declared carried.

 

            The Committee agreed to adopt the remaining recommendations as set out in paragraph 4.1 of the report.

 

Supporting documents: