Agenda item

Minutes:

2.0       Key actions for 2014/15

 

The activities and performance indicators outlined in the following two sections demonstrate what the Department will do to implement its value creation map and therefore how it will contribute to the Council’s corporate value creation map.

 

Updates on project milestones and on performance indicators (Section 3) are reported to DMT on a quarterly basis and are used to inform Committee reports.

 

 

2014-15 Action

LGR or Investment Programme

 

City Leadership

 

1

Lead on the organisational change programme attached to the reform of local government.

LGR

2

Engage and provide strategic advice and technical support to the local government reform regional implementation structures (including the Regional Transition Committee, Regional Operational Board and technical implementation groups)

LGR

3

Establish and oversee implementation of the work plan for the regional Financial Planning Sub-Group and regional Financial Guidance and Audit Sub-Group

LGR

4

Support the Council’s engagement and input to the work of the Regional Systems Convergence Working Group

LGR

6

Oversee the process of detailed due diligence and baseline verification of the resources (budget and staffing) and assets and liabilities attached to the functions and powers transferring from central to local government

LGR

5

Provide technical support and advice in relation to regional preparations for systems convergence linked to the transfer of functions and powers

LGR

7

Oversee the Council’s preparation for the transfer and integration of new central government functions

LGR

8

Ensure that an integrated approach is taken to addressing the key organisational support issues and planning requirements for local government reform

LGR

9

Support the Council’s performance and programme management infrastructure and prepare for the performance management of transferring functions (to include planning, regeneration, service standards)

LGR

10

Prepare for emerging legislative and governance changes including the review of BCC governance and political management arrangements (and review Audit Panel role/Committee arrangements in light of new governance arrangements)

LGR

 

Economy

 

11

Implement the non capital elements of the Super Connected Belfast project

IP

12

Sustain and enhance the rates base and manage the rate setting process including developing a programme of work on ongoing debt and vacant property

IP

13

Improve payment systems to ensure we pay 90% of our creditors within 28 days to support the local economy

IP

 

Improving Our Services

 

14

Prepare the Department for the LGR boundary extension by designing and delivering a budget and transition plan for services and resources merging across the new council area on 1st April 2015.

LGR

15

Deliver the corporate Efficiency Programme in order to maintain the district rate increase at, or below, the rate of inflation

IP

 

Financial Planning

 

16

Manage financial planning for local government reform (to include the capital financing strategy and financial planning for new Council)

LGR

17

Prepare for the 2015/16 rate setting process (to include guidance to departments, medium term financial plan, funding allocation model for transfer of functions)

LGR

18

Develop a reporting framework for financial reporting to the Shadow Council in 2014/15 

LGR

19

Develop a financial governance framework for the new Council (to include financial regulations and Account Manual)

LGR

20

Provide support and guidance on the finance stream of the Leisure Transformation Programme

 

21

Implement the financial management arrangements for the Capital Programme including the Belfast Investment Fund and the Local Investment Fund

 

22

Implement the City Financing Strategy

 

23

Implement a financial improvement programme in relation to debtors

 

 

Information Management

 

24

Undertake the necessary ICT preparations linked to the transfer of new functions and the extension to the Council boundary

LGR

25

Continue to improve information management processes in the Department 

 

26

Develop an ICT Strategy and Plan to support the delivery of the Council’s priorities

 

27

Develop a mobile and online programme of work in line with new ICT strategy

 

28

Implement actions form the Information Governance Group

 

29

Continue to integrate systems with the corporate common address database and Gazetteer

 


 

30

Develop an approach and specification for the purchase of a replacement HR/Payroll system and implement the system

 

31

Procure a corporate property information system 

 

 

Planning & Performance

 

32

Further enhance the performance and accountability framework in the Council in the context of community planning

LGR

 

Communication and Engagement

 

33

Improve internal communications across the department

 

 

Governance & Risk

 

34

Plan for the implications of the transfer of functions and boundary changes on the Audit, Governance and Risk Management Service (including the Health and Safety Unit)

LGR

35

Provide assurance on the Council’s approach to preparing for the transfer of new functions and powers and the extension to the Council boundary

LGR

36

Include provision for new functional areas and integrated reporting within the action tracking, risk management and audit management system

LGR

37

Provide support and guidance on the audit, assurance and risk requirements of the Leisure Transformation Programme 

 

38

Implement recommendations arising from the external review of the Council’s Health and Safety service

 

 


3.0       Key performance indicators for 2014/15

 

3.1       Environment

 

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

% Volume of Colour Print – Corporate Total

% Volume of Duplex Print – Corporate Total

% Volume of Colour Print – Dept Total

% Volume of Duplex Print –Dept Total

30%

40%

30%

40%

30%

40%

30%

40%

 

3.2       Improving our Services

 

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

Number of complaints received - All Corporate Total

0

0

% Complaints that met response target– All  Corporate Total 

100%

100%

Number of complaints received – Departmental

0

0

% Complaints that met response target– Departmental total  

100%

100%

Value of efficiency savings captured as part of the estimating process

£2m

£2m

Variance between actual efficiencies against target 

100%

100%

Number of transactional based activities which are e-enabled  

No target

TBA

 

3.3       Human Resources

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

Average number of working days lost due to absence – Dept Total

7.44 days

7.44 days

% staff across the department with an up to date PDP - Part 1 Process 

90%

90%

 


 

3.4       Financial Planning

 

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

% Compliance of GRN’s after invoicing – Corp Total

% Compliance of GRN’s after invoicing – Dept  Total

75%

75%

75%

75%

% Compliance of PO’s raised on time – Corp Total

% Compliance of PO’s raised on time – Dept  Total

90%

90%

90%

90%

% Debt  less than 90 days old

65%

     65%

 

% Increase in the District Rate

0%

At or below inflation

% variance between actual net revenue expenditure and budgeted net revenue expenditure (in year) [Qlikview] (Corporate)

-2.00% to +1.00%

 -2.00% to +1.00%

% variance between forecast  net revenue expenditure and actual net revenue expenditure (year end) [Qlikview] (Corporate)

-2.00% to +1.00%

-2.00% to +1.00%

% creditors paid within 28 days [Qlikview] (Corporate)

90%

90%

 

3.5       Information Management

 

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

% Time Key Systems available (Uptime)

100%

100%

Number of systems aligned to the Gazetteer

No target

TBA

 

3.6       Policy, Planning and Performance

 

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

% PIs updated – Corporate total

% PIs updated–Departmental total

% PIs on target – Corporate total

% PIs on target –  Departmental total

85%

85%

70%

70%

85%

85%

70%

70%

 

 


 

3.7       Governance & Risk

 

Performance Indicator

Annual Target
2013-14

Annual Target
2014-15

%  AGRS Plan completed annually

70%

70%

Number of RIDDOR accidents

48

Monitoring indicator

% H&S recommendations fully implemented – Corporate Total

80%

80%

% H&S recommendations fully implemented-- Department Total

80%

80%

% H&S Plan completed annually

75%

75%

Number of workplace accidents

380

Monitoring indicator

% Workplace Health & Safety inspections

80%

80%