· Approved the public advertisement of tenders as per Standing Order 37a detailed in Appendix 1 (Table 1) subject to the omission of the tenders in relation to Provision of temporary agency workers (neutral vendor model) and Provision of temporary agency workers using call-off framework (where neutral vendor cannot provide a suitable candidate in a timely manner). The Committee agreed that the aforementioned two tenders be deferred so that further information could be provided at its meeting in October;
· Approved the award of STAs in line with Standing Order 55 exceptions as detailed in Appendix 1 (Table 2);
· Approved the modification of the contract as per Standing Order 37a detailed in Appendix 1 (Table 3) subject to the omission of the tender Hire of Skips - CNS Q24.15. The Committee agreed that the aforementioned tender be deferred so that further information could be provided at its Special meeting on Friday, 26th September;
· Approved an amendment to the current funding agreement with Visit Belfast as detailed in section 6.0; and
· Agreed that a report be submitted in relation to the governance and scrutiny of Contracts, to include detail on the effectiveness and social value of contracts.
Table 1: Competitive Tenders
|
Title of Tender |
Proposed Contract Duration |
Est. Max Contract Value |
SRO |
Short description of goods / services |
|
Replacement boilers & associated works at Tropical Ravine Botanic Gardens |
Up to 3 months |
£150,000 |
S Grimes |
Supply and installation of replacement boilers due to failure of 3No existing boilers – currently inadequate heating media to sustain the specialist flora located. |
|
Supply and installation of Solar PV on roof for Donegal Pass Community Centre Fully Funded |
Up to 2 months |
£45,000 |
S Grimes |
The solar panels will generate electricity to be used by the Community Centre reducing its energy consumption, electricity costs and CO2e emissions |
|
Provision of porterage and storage services |
Up to 2 years |
£90,000 |
N Largey |
Service for the moving of various furniture and other items between BCC buildings. Service is not currently available within BCC. Dept considering in-house options but require a contract up to 2 years to ensure continuity of service whilst this review is conducted. |
|
Accommodation/ hotel services (Bed and breakfast basis) to support the delivery of Fleadh Cheoil na hÉireann 2026. |
Up to 2 weeks |
£220,000 |
D Martin |
The contractual agreement between Council and Comhaltas includes the provision of hotel accommodation and business suite facilities to support the delivery of Fleadh Cheoil na hÉireann 2026. |
Table 2: Single Tender Actions
|
Title |
Duration |
Est. Max Contract Value |
SRO |
Description |
Supplier |
STA Reason |
|
Corporate HR & Payroll system for Belfast City Council |
Up to 3 years |
£1,230,000 |
S McNicholl |
Zellis were awarded the Corporate HR & Payroll system contract in 2016 following a competitive tender exercise using the Crown Commercial framework contract for Corporate Software Solutions.
Implementation of this new HR & payroll system has proven to be complex with some elements of the implementation still ongoing.
A 3 year STA is therefore required to support the completion of the implementation, including potentially moving to a Cloud based solution with Zellis, and for the council to consider its longer term procurement options for software licensing & maintenance of the system.
There are no other current procurement options available to appoint Zellis. This may change once the system is moved to a Cloud based solution.
Zellis are the owners of the software. Software licensing & maintenance cannot be provided by any other supplier. |
Zellis UK Ltd |
3 |
Table 3: Modification to Contract
|
Title of Contract |
Original Contract Duration & Value |
Modification |
SRO |
Description |
Supplier |
|
Supply and delivery of paint and sundries – T2015 |
Up to 4 years 6 months & £132k |
Additional 2 months and £6,000 |
S Grimes |
The new tender (T2517) is at evaluation stage. The product testing stage of the evaluation is ongoing and award has been delayed as 1st placed supplier failed this testing process as their products did not meet specification following testing. Testing process now started with 2nd place supplier. The testing process is critical to ensure we buy quality paint products to support operational maintenance teams and reduce associated costs. Con Mod approved Feb 2025 for additional 4 months and £6,000 and Jun 2025 for additional 3 months and £6,000 |
PPG Architectural
|
Supporting documents: